60 percent of road construction completed - News.MN

60 percent of road construction completed

Old News! Published on: 2011.08.30

60 percent of road construction completed

Avatar
Мөнгөнтамир
Uncategorized
With the new school year just beginning, fears of traffic jams abound. Today a high-ranking official in the Auto Road Office said 60 percent of planned road construction has been completed. S. Tumendemberel, a senior engineer for road operation and repair for the Auto Road Office said 4.2 meters of a planned 6.7-meter road project in Dari-Ekh has been finished. In a street named Ajilchnii gudamj, a 1,680-meter long stretch of road from Gurvaljin Bridge has been completed. And a road to Sonsgolon is scheduled to be opened today. However, a road from Dund gol to TETS-3 is still blocked by road construction.