First phase of Salkhit wind farm commissioned - News.MN

First phase of Salkhit wind farm commissioned

Old News! Published on: 2013.06.18

First phase of Salkhit wind farm commissioned

Avatar
Ш. Адъяамаа
Uncategorized
The State Commission  held an event to accept the completion of the first phase of the 50MW Salkhit wind farm in Ministry of Energy on Monday June 17th.  The wind farm, part of Mongolia”s first wind power project in Sergelen sum of Tuv aimag, is currently under construction.

The State Commission approved a 110/35 kw sub-station, 110 kw explicit transmission facility, 35 kw transmission facility building, 15 wind turbine generators and a 110 kw electricity transmission line from the wind farm.

The State Commission was formed under a regulation permitting the start-up, duration and commissioning for construction enacted by Government resolution 151. The State Commission reviewed the quality, legal acts and documents of Salkhit wind farm as requested by the project developer Clean Energy LLC. The decision was reached to approve it as a Hydro Power Station based on Articles of the law on construction with 100 percent approvals from the commission members. 

It has also been approved to simultaneous do testing and connecting of the second phase of Salkhit wind farm to the network as the State Commission agreed with the National Network of Power Transmission LLC and the National Dispatching Center.

The opening ceremony for the “Salkhit” 50 megawatt (MW) wind farm developed by Clean Energy, a subsidiary of Newcom group, will happen on June 20th.

For your Reactions?
0
HeartHeart
0
HahaHaha
0
LoveLove
0
WowWow
0
YayYay
0
SadSad
0
PoopPoop
0
AngryAngry
Voted Thanks!